Project timeline
From industrial park registration to full launch — 48 months of step-by-step development (Q4 2025 — Q4 2029).
4 years — 48 months
The park will be launched in stages: registration, design, construction of networks and facilities, parallel launch of the first residents.
Industrial park registration
Inclusion in the official Register of Industrial Parks of Ukraine. Duration: 5 months.
Managing company appointment
ITAL INVESTMENT LLC officially becomes the managing company and starts work with participants. Duration: 6 months.
Participant onboarding & financing
Signing agreements with residents, attracting private investors and state incentives. Duration: 24 months.
Network design
Preparation of design and estimate documents for power, gas, water and roads. Duration: 12 months.
Network construction
Laying utility networks: water, gas, electricity, roads, landscaping. Duration: 18 months.
Facility design
Design of industrial, warehouse, administrative and technical buildings. Duration: 24 months.
Facility construction
Construction of industrial facilities, warehouses, office buildings and technical structures. Duration: 30 months.
First residents launch
Start of production activities of the first park residents. Duration: 3 months.
Full park launch
Full commissioning of all infrastructure and facilities. The park operates at full capacity.
Industrial parks of Ukraine
As of November 2025, the Ukrainian register lists 107 industrial parks, 32 of which are operational. Khorvatsky Hostynets is part of the growth of Western Ukraine's private parks.
107
Total in register
industrial parks of Ukraine in 2025
32
Operational
industrial parks today
+16
Registered in 2025
new parks in Ukraine
1.1 bn
State incentives 2024
UAH received by 15 parks
Ready to start cooperation?
The best moment to become a resident is at the design stage. Contact us to discuss terms.